Major project in the Vlaketunnel
Text Roel van Gils Image Jennissen

The Vlaketunnel in Zeeland was completely closed for ten days in April for major maintenance. During this short period, the tunnel received a new asphalt surface, among other work. Jennissen removed the existing asphalt in both tunnel tubes at record speed. No fewer than seven rippers were used simultaneously. The contractor called on SAES International for the job.
Working for Gebr. Van Kessel, Jennissen removed the asphalt in the Vlaketunnel down to the concrete. The 8 cm layer covered around 12,000 m². The team deployed heavy machinery for this major project. Seven excavators fitted with rippers worked simultaneously, supported by a wheel loader and an extra excavator at the stockpile area. The asphalt slabs removed were taken away immediately.
Five new rippers
Jennissen initially had three rippers, but these proved insufficient for a project of this scale. So the company approached SAES. In a short time, SAES built five rippers tailored entirely to Jennissen’s requirements. “That meant we could rip with seven excavators at once, significantly increasing productivity,” says project manager Pieter Pels. The results speak for themselves: in two 16-hour shifts, 6,000 m² of asphalt was removed each time. “We started on Thursday with the first tunnel tube, and the contractor was able to lay new asphalt there as early as Saturday,” Pels explains. “Work on the second tunnel tube, in the direction of travel from Zeeland to Brabant, began on Monday. Here too, the job was finished within sixteen hours, so the new asphalt surface could be laid two days later.”



Excellent service
The partnership with SAES once again proved highly valuable. The company had previously supplied two rippers and various other attachments, and this time too, it responded quickly. “They provide excellent service,” says Pels, who also praises SAES’s flexibility and availability, as well as its ability to respond quickly to specific customer needs. In addition to buying equipment, with all five rippers purchased by Jennissen, the company also regularly uses SAES’s rental service. “We recently hired a hydraulic breaker for a project in Maasbree,” says Pels. “It was delivered to the site in good order, with a technician setting it up, including fine-tuning it on site. We got the most out of it, as the breaker performed optimally throughout the project.”
Jennissen’s work in the Vlaketunnel was part of a larger ten-day operation. As well as the asphalt, the team also worked on the expansion joints and replaced the crash barriers. Looking ahead, Pels expects to see more large-scale projects of this kind. “Investing in the five rippers was a strategic decision,” he says. “The successful completion of the work in the Vlaketunnel shows what can be achieved with the right preparation, people and partners around us.”
Een zakelijke vraag aan Saes International BV? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectNews
- CompanySaes International BV